KANO EDC Second Suspension

1. The Independent System Operator, on behalf of the Market Operator, entered into a Market

Participation Agreement with Kano Electricity Distribution PLC (KEDCO) on the 6th of February

2015.

2. In the signed Market Participation Agreement, KEDCO agreed to at all times be compliant with

the provisions of Clause 3.2 reproduced below:

The Participant shall in accordance with the provisions of the Market Rules, Grid Code, Metering Code and the Market Procedures be compliant at all times, particularly by:

i. Providing metering information in a timely manner and in the approved format in accordance with the Metering Code and the market procedures.

ii. Security Deposit when so required of an amount established by Market Operator to serve as a form of guarantee of payment for all amounts due

from the Participant to the Market Operator.

iii. Settling in a timely manner any payment due