KANO EDC DISCONNECTION ORDER PDF Print E-mail
Written by Market Operator   
Thursday, 25 July 2019 02:46

TRANSMISSION COMPANY OF NIGERIA (TCN)

INDEPENDENT SYSTEM OPERATOR

Order No: TCN/ISO/MO/2019/006

Before the Market Operator, Independent System Operator, Transmission Company of Nigeria.

In the matter of non-compliance with the conditions of Market Rules and Market Participation Agreements.

WHEREAS:

1. That Kano Electricity Distribution Company (KEDCO) is under suspension through Market Operator issued Order TCN/ISO/MO/005.

2. That Kano Electricity Distribution Company (KEDCO) has been suspended from the Market Operator Administered Market due to an EVENT OF DEFAULT that was not remedied. KEDCO was notified of this EVENT OF DEFAULT by a NOTICE OF EVENT OF DEFAULT (NED/2019/004) dated July 9TH, 2019.

3. In line with Section 45.3.7 of the Market Rules KEDCO was issued a “Notice of Intent to Issue Suspension Order

Last Updated on Thursday, 25 July 2019 03:01
Read more...
 
KANO EDC SUSPENSION ORDER PDF Print E-mail
Written by Market Operator   
Thursday, 25 July 2019 02:38

TRANSMISSION COMPANY OF NIGERIA(TCN)

INDEPENDENT SYSTEM OPERATOR


ORDER NO: TCN/ISO/MO/2019/005

BEFORE THE MARKET OPERATOR, INDEPENDENT SYSTEM OPERATOR, TRANSMISSION COMPANY OF NIGERIA

IN THE MATTER OF NON-COMPLIANCE WITH THE CONDITIONS OF MARKET RULES AND MARKET PARTICIPATION AGREEMENTS.

WHEREAS:

1.The Independent System Operator, on behalf of the Market Operator, entered into a Market Participation Agreement with Kano Electricity Distribution PLC (KEDCO) on the 6th of February 2015.

2.In the signed Market Participation Agreement, KEDCO agreed to at all times be compliant with the provisions of Clause 3.2 reproduced below:

The Participant shall in accordance with the provisions of the Market Rules, Grid Code, Metering Code and the Market Procedures be compliant at all times, particularly by:

Last Updated on Thursday, 25 July 2019 03:02
Read more...
 
Notice of Lifting Suspension and Disconnection Order 002-003 for EEDC PDF Print E-mail
Written by Onem Public Affairs   
Friday, 05 July 2019 18:00

TRANSMISSION COMPANY OF NIGERIA (TCN)

INDEPENDENT SYSTEM OPERATOR

Notice of Lifting Suspension Order

(Order: TCN/ISO/MO/2019/002)

&

Notice of Lifting Disconnection Order

(Order: TCN/ISO/MO/2019/003)

issued against Enugu Electricity Distribution Company

Before the Market Operator, Independent System Operator, Transmission Company of Nigeria.

In the matter of non-compliance with the Market Rules and Market Participation Agreements.

WHEREAS:

  1. Enugu Electricity Distribution Company (EEDC) was suspended from the Market Operator Administered Market due to an EVENT OF DEFAULT. EEDC was notified of this EVENT OF DEFAULT by a NOTICE OF EVENT OF DEFAULT (NED/2019/002) dated May 24, 2019.

Last Updated on Friday, 05 July 2019 21:45
Read more...
 
Lifting of Suspension Order against EKEDC PDF Print E-mail
Written by Onem Public Affairs   
Wednesday, 03 July 2019 21:51

TRANSMISSION COMPANY OF NIGERIA (TCN)

INDEPENDENT SYSTEM OPERATOR

Notice of Lifting Suspension Order

(Order: TCN/ISO/MO/2019/001)

Issued against Eko Electricity Distribution Company Before the Market Operator, Independent System Operator,

Transmission Company of Nigeria.

In the matter of non-compliance with the conditions of Market Rules and Market Participation Agreements.

WHEREAS:

1. Eko Electricity Distribution Company (EKEDC) was suspended from the Market Operator Administered Market due to an EVENT OF DEFAULT. EKEDC was noticed of this EVENT OF DEFAULT by a NOTICE OF EVENT OF DEFAULT (NED/2019/001) dated May 24, 2019.

Last Updated on Thursday, 04 July 2019 04:48
Read more...
 
Lifting of Suspension Order against IKEDC PDF Print E-mail
Written by Onem Public Affairs   
Wednesday, 03 July 2019 21:19

TRANSMISSION COMPANY OF NIGERIA (TCN)

INDEPENDENT SYSTEM OPERATOR

Notice of Lifting Suspension Order

(Order: TCN/ISO/MO/2019/004)

Issued against Ikeja Electricity Distribution Company Before the Market Operator, Independent System Operator, Transmission Company of Nigeria.

In the matter of non-compliance with the conditions of Market Rules and Market Participation Agreements.

WHEREAS:

1. Ikeja Electricity Distribution Company (IKEDC) was suspended from the Market Operator Administered Market due to an EVENT OF DEFAULT. IKEDC was noticed of this EVENT OF DEFAULT by a NOTICE OF EVENT OF DEFAULT (NED/2019/003) dated May 24, 2019.

Last Updated on Thursday, 04 July 2019 04:49
Read more...
 
Information on Black Start PDF Print E-mail
Written by Regulatory Department   
Thursday, 31 January 2019 11:36

PROVISION OF BLACK START CAPABILITY BY GENERATORS AS ENSHRINED IN THE GRID CODE (GC), MARKET RULES (MR), ANCILLARY SERVICES AGREEMENT (ASA) AND OTHER PROVISIONS CONNECTED THERETO.

...The Grid Code amongst other provisions made Black Start a mandatory Ancillary Services to be contracted by the System Operator. In other words, Generators that are connected to the National Grid must provide Black Start, save for approved derogation.

All necessary contracts must be executed (e.g ASA) between the System Operator and Generators for the provision of Black Start Capability. Kindly see sections 17.1.1, 17.2.1, 17.3.1 and 18 of the Grid Code.

Last Updated on Thursday, 04 April 2019 11:09
Read more...
 